Brownfield Expansion: What the Next Increment Costs

Put this tool on your own site

Paste this where you want the sheet to appear. It works on any site — WordPress, Squarespace, Webflow, Ghost or plain HTML — and needs no JavaScript of yours. Readers get the same tool a visitor here gets without signing in, and a link back for the rest of it.

See what it looks like

Shared plant comes in lumps, so the cost per spindle is a sawtooth. Expanding more is regularly cheaper per spindle than expanding less.

The Proposal

What is being added, and what the machinery quotation says it costs

Spindles, looms or machines - whatever the shared plant below is consumed by

The part that genuinely is linear, and the part nobody gets wrong

The Shared Plant

One row for everything the new capacity draws on that is not bought per machine. Headroom is what is genuinely spare today at the load the mill actually runs, not the nameplate less the design load - a transformer at 78% is not carrying 22% of headroom in July. Step size and step cost are the smallest increment that can actually be bought and what it costs installed, including the civil work and the shutdown, because a step is not a step until it is running.

Shared PlantDrawn per Unit per spindleSpare Today same unitsSmallest Step same unitsCost of a Step costCarries Now unitsProposal Needs same unitsSteps Forced no.Which Cost costThen Carries unitsSpare Afterwards unitsSets the Free Size 1/0Sets the Filled Size 1/0Row actions
————————
————————
————————
————————
————————

Add line opens a form. Cells in the sheet stay directly editable.

How to read this sheet

Machinery is linear and shared plant is not, so capital per unit is a sawtooth: flat until a limit is crossed, a vertical jump when it is, then falling again as the step fills. Two sizes are worth knowing and the space between them is worth avoiding. Below the tightest headroom nothing shared has to be bought and the cost is the machinery cost. Once anything has been bought, the cost per unit keeps falling until the last step bought is full, so an expansion that crosses a limit should usually go much further than the one that crossed it. The dearest size reported is the warning: a modest increment that has crossed every limit and filled none of them, which is exactly the shape of proposal a board approves because it looks prudent. Headroom is the input that decides everything and the one most often overstated. It is what is genuinely spare at the load the mill runs in its worst month, not the nameplate less the design figure - a transformer at 78% in February is not carrying 22% into July, and humidification headroom in particular is a summer number. Step cost should be the installed cost including civil work, cabling and the production lost to the shutdown, because a step that is delivered and not commissioned has bought nothing. What is outside this: whether the market wants the extra output, which is the question that should be asked first and this sheet cannot answer; the working capital a larger expansion needs, which grows with it and is not capital expenditure; the possibility of renting or sharing a step rather than buying it; and any staging over time, since a step bought in three years is cheaper today than one bought now and this sheet prices everything at once.

Textile SchoolBrownfield Expansion: What the Next Increment Costswww.textileschool.com