Home » Professional Tools » Mill Power & Utility Load Schedule
Jump to a calculator 618 tools

ProMill Projects & InvestmentProject Engineering

Mill Power & Utility Load Schedule

Put this tool on your own site

Paste this where you want the sheet to appear. It works on any site — WordPress, Squarespace, Webflow, Ghost or plain HTML — and needs no JavaScript of yours. Readers get the same tool a visitor here gets without signing in, and a link back for the rest of it.

See what it looks like

Connected load is not maximum demand, kW is not kVA, and contract demand is not transformer rating. Each confusion is bought once and billed monthly.

Operation

What the mill runs and what it makes

Three shifts over 330 days is 7,920

Used to express the load as kWh per kilogram

Power Factor

Where kW becomes kVA, and where the demand bill is won

Induction motors without capacitors sit near 0.85

Most tariffs incentivise 0.95 and above

Sizing Margins

Spare capacity is a decision, not a rule of thumb

For growth and for the next standard rating up

Humidification, lighting and the production that must not stop

Ambient temperature and altitude, per the supplier curve

Tariff

Energy is metered; demand is contracted

Billed on contract demand whether drawn or not

Department Load List

Nameplate kW by department, with the load factor each actually works at and the diversity that runs together. Humidification and compressed air belong here: leave them out and the schedule is short by a quarter.

DepartmentConnected kWLoad Factor %Diversity %Demand kWRow actions
—
—
—
—
—
—
—
—

Add line opens a form. Cells in the sheet stay directly editable.

How to read this sheet

Maximum demand here is a design figure built from declared load and diversity factors, not a measured one; a utility bills on the highest half-hour or fifteen-minute average it records, and a mill that starts departments together after a power cut can set a demand peak it then pays for all year, so the transformer spare margin is also a starting-sequence margin. Load factors should come from motor loading measured at a comparable mill rather than from the motor plate, because oversized motors are endemic in textiles and a 30 kW motor doing 18 kW of work reports a load factor of 60 percent, not 100. The specific energy this returns is the whole-mill figure including humidification and compressed air, which is the only basis on which published benchmarks are comparable, and it is the number a feasibility report should carry: where the two disagree, the load schedule is the one built from equipment and the benchmark is the one built from someone else’s mill. Capacitor requirement is the steady-state bank at maximum demand; harmonics from variable frequency drives are not modelled, and a mill with substantial drive load needs detuned reactors rather than plain capacitors, which changes both the cost and the achievable power factor. Generator sizing assumes the essential load can be picked up in stages - a set chosen on running kVA will not start a large motor across the line, and the transient rating is a supplier question this schedule does not answer. Above 5,000 kVA the transformer figure is rounded to a clean step and means more than one unit, which is a different single-line diagram and a different cost.

Textile SchoolMill Power & Utility Load Schedulewww.textileschool.com
Scroll to Top