Jump to a calculator 671 tools
Oekotech
Silt Fence Take-Off: Fabric, Rolls, Posts & Trench for a Site
A silt fence is a strip of fabric with its foot in a trench. The buried toe is fabric too; leave it out and the order comes up short.
Rolls to Order
— rolls
Fabric length with joins and allowance, divided by the roll length, rounded up
Take-Off
- Cut Height of Fabric
- — cm
- Roll Width Left Over (Negative = Too Narrow)
- — cm
- Roll Joins along the Run
- — joins
- Fabric Length incl. Joins
- — m
- Fabric Length incl. Allowance
- — m
- Fabric in the Fence
- — m²
- Share of Fabric Buried in the Toe
- — %
- Posts
- — posts
- Trench to Dig & Backfill
- — m³
Every dimension is the specification's or the plan's: the exposed height, the toe, the post spacing and the join detail differ between authorities and between fabric types, so the tool takes them as inputs and has no figure of its own. Fabric in the fence is the fabric length times the cut height; the order is in whole rolls of the roll width you enter, and if the cut height is wider than the roll the result says so with a negative spare. Posts count both ends of one straight run; a run broken into separate lengths needs one more post per extra length. **This is a quantity take-off, not a design: it does not decide where a silt fence belongs or how much drainage area it can serve.**
Using this calculator
About the Silt Fence Take-Off: Fabric, Rolls, Posts & Trench for a Site
The formula
This is the expression the tool evaluates. Every term is named underneath, with the unit it must be supplied in.
fabricHeight = aboveGround + toeThe fabric runs from the top of the fence down into the trench and along its floor. That buried part is bought fabric like the rest.
pieces = ceil((fenceLength - joinLap) / (rollLength - joinLap))n pieces of length R lapped by o cover n x R - (n - 1) x o, so each join costs one lap of fabric.
rolls = ceil((fenceLength + joins x joinLap) x (1 + wastage / 100) / rollLength)Whole rolls by length, after the joins and the allowance.
posts = ceil(fenceLength / postSpacing) + 1One post per bay plus the closing post. Trench volume is length x width x depth.
| Symbol | Stands for | Unit |
|---|---|---|
fenceLengthM | Fence Length | m |
aboveGroundCm | Fabric Height above Ground | cm |
toeCm | Buried Toe (Trench Depth + Turn) | cm |
trenchWidthCm | Trench Width | cm |
trenchDepthCm | Trench Depth | cm |
postSpacingM | Post Spacing | m |
rollWidthCm | Roll Width | cm |
rollLengthM | Roll Length | m |
joinLapCm | Lap at a Roll Join | cm |
wastagePct | Cutting & Damage Allowance | % |
rollsNeeded | Rolls to Order | rolls |
fabricHeightCm | Cut Height of Fabric | cm |
rollWidthSpareCm | Roll Width Left Over (Negative = Too Narrow) | cm |
rollJoins | Roll Joins along the Run | joins |
fabricLengthM | Fabric Length incl. Joins | m |
fabricWithWasteM | Fabric Length incl. Allowance | m |
fabricAreaM2 | Fabric in the Fence | m² |
buriedSharePct | Share of Fabric Buried in the Toe | % |
posts | Posts | posts |
trenchM3 | Trench to Dig & Backfill | m³ |
How the result is derived
Step by step, from the values you type to the figure on screen.
- The 10 inputs are read from the form on every keystroke: Fence Length, Fabric Height above Ground, Buried Toe (Trench Depth + Turn), Trench Width, Trench Depth, Post Spacing, Roll Width, Roll Length, Lap at a Roll Join and Cutting & Damage Allowance.
- Each value is checked against the accepted range in the input table below. A value outside its range stops the calculation rather than producing a misleading figure — the results blank out and a message appears.
- The validated values are substituted into the expression above, which resolves Rolls to Order together with every supporting figure in one pass — no value is carried over from a previous entry.
- The supporting outputs — Cut Height of Fabric, Roll Width Left Over (Negative = Too Narrow), Roll Joins along the Run, Fabric Length incl. Joins, Fabric Length incl. Allowance, Fabric in the Fence, Share of Fabric Buried in the Toe, Posts and Trench to Dig & Backfill — come from the same pass, so they always describe the same case as the headline figure.
- Results are rounded for display only. The full-precision value is used throughout the chain, so reading a rounded intermediate figure back into the tool by hand can shift the last digit.
What each input means
Where to read each value on the floor, the unit it must be in, and the range the tool accepts.
| Input | Unit | Accepted range | Default | What it means |
|---|---|---|---|---|
| Fence Length | m | 5 to 100000 m | 200 | The whole run, including the ends turned uphill. |
| Fabric Height above Ground | cm | 20 to 150 cm | 60 | The exposed height the specification sets. |
| Buried Toe (Trench Depth + Turn) | cm | 0 to 100 cm | 30 | Fabric carried down the trench wall and turned along its floor before backfill. |
| Trench Width | cm | 5 to 60 cm | 15 | |
| Trench Depth | cm | 5 to 60 cm | 15 | |
| Post Spacing | m | 0.5 to 5 m | 2 | |
| Roll Width | cm | 30 to 500 cm | 91 | Silt fence fabric is sold slit to height; the roll width is the height you can cut. |
| Roll Length | m | 10 to 1000 m | 100 | |
| Lap at a Roll Join | cm | 0 to 300 cm | 50 | Fabric overlapped or wrapped round a shared post where one roll ends and the next starts. |
| Cutting & Damage Allowance | % | 0 to 50 % | 5 | A planning figure, not a measured loss. |
What the tool returns
The headline figure and every supporting value it is built from.
| Output | Unit | What it tells you |
|---|---|---|
| Rolls to Order (headline result) | rolls | Fabric length with joins and allowance, divided by the roll length, rounded up |
| Cut Height of Fabric | cm | |
| Roll Width Left Over (Negative = Too Narrow) | cm | |
| Roll Joins along the Run | joins | |
| Fabric Length incl. Joins | m | |
| Fabric Length incl. Allowance | m | |
| Fabric in the Fence | m² | |
| Share of Fabric Buried in the Toe | % | |
| Posts | posts | |
| Trench to Dig & Backfill | m³ |
Worked example
Given
- Run
- 200 m, 60 cm above ground, 30 cm toe, 15 x 15 cm trench
- Roll
- 91 cm x 100 m, 50 cm join lap
- Posts
- 2 m spacing
- Allowance
- 5%
Substituting
60 + 30 = 90 cm cut height; 91 - 90 = 1 cm of roll to spare(200 - 0.5) / (100 - 0.5) = 2.005, so 3 pieces and 2 joins; 200 + 2 x 0.5 = 201 m201 x 1.05 = 211.05 m; / 100 = 2.11, so 3 rollsfabric in the fence 201 x 0.90 = 180.9 m², a third of it (30/90) buried200 / 2 = 100 bays, 101 posts; trench 200 x 0.15 x 0.15 = 4.5 m³Answer
- Cut height
- 90 cm, 1 cm spare on the roll
- Fabric
- 201 m in the fence, 211.05 m with allowance
- Rolls
- 3
- Posts
- 101
200 m of fence looks like two 100 m rolls. The two laps alone make it three, before any allowance.
How to use it
- Work through the input groups in order — Fence Line and Posts, Roll & Allowance. The defaults are a realistic case, so you can change one value at a time and watch what moves.
- There is no calculate button. Every figure recalculates as you type or drag, which is what makes this usable for a what-if sweep rather than a single answer.
- Read Rolls to Order in the dark results panel — that is the headline figure, expressed in rolls.
- Check the supporting rows underneath (Cut Height of Fabric, Roll Width Left Over (Negative = Too Narrow), Roll Joins along the Run, Fabric Length incl. Joins, Fabric Length incl. Allowance, Fabric in the Fence, Share of Fabric Buried in the Toe, Posts and Trench to Dig & Backfill) before acting on the headline — they are where an implausible input usually shows itself first.
- Reset to defaults returns every field to the reference case, which is the quickest way to check whether a surprising result came from the tool or from an input you had changed earlier.
Where this is used
- Process planning — establishing Rolls to Order before a trial is booked, so machine time and material in Geosynthetics & Civil Engineering are committed against a calculated figure rather than an estimate.
- Costing and quotation — Rolls to Order is an input to the cost sheet, and quoting from a worked number rather than a remembered one is what keeps a margin intact.
- Troubleshooting — when the floor result drifts from plan, entering the measured values (starting with Fence Length) shows how much of the gap in Rolls to Order each variable explains.
- Teaching and study — the accepted ranges bracket normal Geosynthetics & Civil Engineering practice, so moving one variable at a time shows the shape of the relationship rather than a single answer.
Reading the result
Typical bands and what each one is telling you.
| Value | What it indicates |
|---|---|
| Negative roll width left over | The roll is narrower than the cut height. Buy the next roll width up, or reduce the toe only if the specification allows it. |
| Fence length just over a whole number of rolls | The laps tip it into another roll. A part roll from another run may cover it; otherwise order it. |
| Buried share above a third | A deep toe on a low fence. Correct if the specification asks for it; check it is not a units slip. |
Assumptions and limits
- Every dimension is the specification's or the plan's: the exposed height, the toe, the post spacing and the join detail differ between authorities and between fabric types, so the tool takes them as inputs and has no figure of its own. Fabric in the fence is the fabric length times the cut height; the order is in whole rolls of the roll width you enter, and if the cut height is wider than the roll the result says so with a negative spare. Posts count both ends of one straight run; a run broken into separate lengths needs one more post per extra length. **This is a quantity take-off, not a design: it does not decide where a silt fence belongs or how much drainage area it can serve.**
- Every input is bounded to the range normal practice occupies (Fence Length 5 to 100000 m, Fabric Height above Ground 20 to 150 cm and Buried Toe (Trench Depth + Turn) 0 to 100 cm, and so on for the rest). Those bounds are guard rails against typing errors, not a claim that the formula fails one unit outside them.
- The calculation is deterministic: the same inputs always give the same result. It carries no allowance for machine condition, operator skill, ambient conditions or lot-to-lot material variation unless an input above explicitly represents one.
- Nothing is sent anywhere. The maths runs in your browser, so the numbers you type never leave the page.
Standards and further reading
- ASTM D6461, Standard Specification for Silt Fence Materials: the fabric properties a specification calls for.
- ASTM D6462, Standard Practice for Silt Fence Installation: the trench, toe, post and join practice the inputs describe.
- AASHTO M 288, Geosynthetic Specification for Highway Applications, which includes temporary silt fence.
- The local erosion and sediment control manual, which sets where silt fence may be used and the dimensions on the plan.
Questions people ask
Why is the buried toe counted?
Because the fabric is cut to the full height, toe included, and the toe is what stops water running under the fence. Leave it out and the order is short by the whole buried strip.
Can I use a wider geotextile roll and slit it?
If the specification allows a site-cut fabric, yes: enter the wide roll's width and the spare shows what each slit leaves. Pre-slit silt fence rolls avoid the cutting.
How do the ends of the fence count?
Enter them in the fence length. Ends turned uphill so water cannot run round the fence are fabric, posts and trench like any other metre.