Home » Professional Tools » Sewing Line Balance Board
Jump to a calculator 618 tools

ProFactory Operations & ProductivityIndustrial Engineering

Sewing Line Balance Board

Put this tool on your own site

Paste this where you want the sheet to appear. It works on any site — WordPress, Squarespace, Webflow, Ghost or plain HTML — and needs no JavaScript of yours. Readers get the same tool a visitor here gets without signing in, and a link back for the rest of it.

See what it looks like

A line produces at the rate of its slowest station, not at the rate of its operators. The difference is fifteen to thirty percent on a typical bulletin, and it is paid for every shift.

Shift

The time the line is available, not the time it is paid for

Net of breaks. Eight hours less a 30 minute break is 450

Used only to express the daily figure

Target

What the line is being asked for

Staffing is solved back from this. Zero to skip

Cost of a Line Position

What an idle minute costs, which is the same as a working one

Fully loaded hourly cost of one operator

Absorbed on the same line hour as labour

Operation Bulletin

Every operation on the line, with the operators allocated to it. Helpers and off-line operations belong here too if they are paid from this line: leaving them out flatters the efficiency without changing the wage bill.

OperationSMV minOperators no.Station Time min/pcIdle vs Bottleneck %Row actions
——
——
——
——
——
——
——
——
——

Add line opens a form. Cells in the sheet stay directly editable.

How to read this sheet

Station time is SMV divided by the operators on that operation, so the balancing lever is the allocation and not the method: re-engineering an operation changes its SMV and belongs upstream of this board. The bottleneck is read from the station times as staffed, which means adding an operator anywhere except the bottleneck moves the output figure not at all - the board will show it, and it is the fastest way to settle the argument. Output is reported as a rate rather than a plan: it assumes the line is fed, that there is no starvation from cutting and no blockage at packing, and that the bundle system holds enough work in process to keep every station covered. Real lines lose further output to absenteeism, machine breakdown, style change and the learning curve at the start of a run, none of which are modelled here, so treat this figure as the ceiling that balance permits rather than the output a shift will book. Operators required for a target is solved per operation and rounded up, because operators are whole people; the theoretical minimum beside it is the same arithmetic without that rounding, and it is unreachable rather than merely ambitious. An operation carrying work with nobody allocated stops the line, so the board reports zero output and counts the unstaffed operations rather than quietly reporting what the staffed stations would have made. Idle minutes are counted as paid minutes less the minutes the pieces consumed, which attributes to imbalance the whole of the difference - including any part of it a supervisor could not have removed by reallocation, since the wage bill does not distinguish.